Delorean hits major bioenergy project milestone with $62.1m financial close
Delorean secures financial close on its $62.1m Horsley Park bioenergy project$30.5m in government grants activated, with Brickworks locked in for 25 yearsConstruction set for early 2027, with major emissions reductions…

- Delorean secures financial close on its $62.1m Horsley Park bioenergy project
- $30.5m in government grants activated, with Brickworks locked in for 25 years
- Construction set for early 2027, with major emissions reductions expected
Special Report: Delorean Corporation has reached a major funding milestone for its $62.1 million Horsley Park bioenergy project, clearing the way to turn organic waste into renewable gas for one of Australia’s biggest brick manufacturers.
Delorean Corporation (ASX:DEL) can now move into procurement, with construction scheduled for early 2027.
It’s a major step forward for the Australian bioenergy developer – bringing together $30.5 million in government grants, a $20 million Westpac finance facility and a 25-year renewable gas supply agreement with Brickworks.
Financial close follows Delorean’s final investment decision in April and activates the key funding, supply and land agreements needed to advance the project.
The facility will be built alongside Brickworks’ manufacturing operations, converting organic waste diverted from landfill into renewable gas for brick production.
And the numbers are substantial.
Once operational, NSW1 is designed to process 120,000 tonnes of organic waste annually and produce approximately 253,000 gigajoules of renewable gas.
That gas is expected to reduce natural gas consumption at Brickworks’ Horsley Park plant by around 50%, while cutting its direct Scope 1 emissions by approximately 38%.
Delorean managing director Joe Oliver described the achievement as a significant moment for the company and the wider industry.
“Reaching Financial Close on NSW1 is a major milestone for Delorean and for Australia’s biomethane industry, following on from Delorean’s 100%-owned SA1 Project now approaching commissioning in Adelaide.”
$62.1m funding package comes together
The funding package combines government support, bank financing, existing project expenditure and additional capital.
The NSW Government is contributing $20 million through its Net Zero Manufacturing Initiative, while the Australian Renewable Energy Agency (ARENA) is providing another $10.5 million under its National Industrial Transformation Program.
Both grant agreements are now active.
Westpac has also executed a $20 million trade finance facility with Delorean’s subsidiary, Horsley Park Bioenergy Pty Ltd, to fund equipment purchases.
The facility carries interest at BBSY plus 2.5%, a 1% line fee and gives Westpac senior security over the project company.
Delorean intends to refinance it into longer-term project debt once NSW1 is commissioned.
The remaining funding comprises $1.6 million already spent on project capital costs, $8.7 million from a combination of new Tanarra financing, R&D tax refunds and future Delorean cash on hand, plus $1.3 million from an equity placement.
Delorean has also secured $1.4 million in placement commitments at 6.7 cents per share, with PAC Partners managing the raise.
The price represents a 15% discount to its last close and 22% to its 15-day VWAP.
Funds will support NSW1 and working capital, with new shares expected to trade from November 17.
Delorean has also entered into a binding term sheet with Tanarra Restructuring Partners for a loan facility of up to $10 million, available in five optional $2 million tranches.
The facility matures in September 2028 and carries cash interest at BBSY plus 8%, subject to a 4% BBSY floor, together with 5% capitalising interest.
It also carries a 3.25% annual commitment fee on undrawn, unexpired tranches, with an additional 5% of cash interest able to be capitalised during the first 12 months.
Drawing on the facility would trigger the progressive issue of zero-exercise-price equity options over NSW1, potentially reducing Delorean’s ownership.
Those options represent project equity interests of 8%, 6%, 5%, 3% and 3% across the five tranches, respectively, and only apply when the corresponding tranche is drawn.
Full legal documentation remains to be executed.
Brickworks locked in for 25 years
One of NSW1’s biggest commercial attractions is that it already has a long-term customer for its renewable gas.
Under agreements activated at financial close, Brickworks will purchase all renewable gas produced by the facility, subject to agreed maximum quantities, over 25 years.
The project will sit on Brickworks-owned land under a 25-year lease, including a rent-free construction period.
Rather than supplying gas into a distant market, NSW1 will produce mains-grade biomethane and pipe it directly to Brickworks’ manufacturing operations behind the meter.
The arrangement gives Delorean a long-term industrial customer while helping Brickworks reduce its reliance on conventional natural gas.
Brickworks is also entitled to purchase Australian Carbon Credit Units and Renewable Fuel Certificates generated by the project.
“With the support of the NSW Government, ARENA, Westpac, Tanarra, Brickworks and of course our shareholders, we can now build and own critical organic waste processing infrastructure on Sydney’s doorstep, delivering renewable gas to Brickworks for decades,” Oliver said.
The facility has development approval for up to 150,000 tonnes of organic waste processing annually, above its initial planned capacity of 120,000 tonnes.
It has a minimum project life of 25 years, aligning with the lease and gas supply agreements.
Construction next as Delorean builds its pipeline
With financial close achieved, Delorean Engineering can now begin procurement and prepare to mobilise to the Horsley Park site.
Construction is scheduled to commence in the first quarter of 2027, following development approval granted in July 2025.
The next steps include procuring equipment, mobilising for construction and finalising the Tanarra facility documentation.
For Delorean, the significance extends beyond a single project.
NSW1 represents another opportunity to build, own and operate renewable energy infrastructure, with revenues expected from long-term contracts and merchant activities.
It also follows the company’s SA1 development in Adelaide, which management says is approaching commissioning.
Oliver said the project would contribute to Delorean’s growing portfolio of revenue-generating infrastructure.
“The project will deliver diverse long term contracted and merchant revenues, which will continue to layer up as Delorean continues to close out and construct its development pipeline.”
With the funding package in place, Delorean’s focus now turns to execution, with procurement starting immediately and construction targeted for early next year.
This article was developed in collaboration with Delorean Corporation, a Stockhead advertiser at the time of publishing.
This article does not constitute financial product advice. You should consider obtaining independent financial advice before making any financial decisions.